A disciplined receiving inspection is cheap compared with the cost of a late-found fault. This article sets out a practical sequence for site teams receiving gensets, engines and major skid-mounted equipment.
Prepare before the truck arrives
Receiving starts with preparation. Have the purchase order, packing list, bill of lading or waybill and any inspection certificates on hand, a named receiving engineer, a camera with a clear date stamp and a laydown area that is firm, level and drained.
Check that the lifting plan and equipment match the weight and lifting points of the load, and that access roads and gates are clear. If the unloading crew meets a problem on arrival, the truck waits and the driver’s clock runs, which can complicate any claim.
Documents first, then the cargo
Compare the delivery documents with the order and the packing list: model, serial numbers, quantities, consignee, weights and marks. A mismatch, such as the wrong alternator frame or a missing item, should be written on the delivery note before the carrier leaves.
Then inspect the packing from outside. Check crates, wrapping and skids for impact marks, water ingress, torn covers or broken lashing. Shock and tilt indicators, where fitted, should be photographed in place and noted; our post on cargo insurance for power equipment explains why that evidence matters.
Inspect the equipment itself
Where the packing allows, inspect the visible parts of the machine: radiators, fan guards, air intakes, exhaust outlets, control panels, terminal boxes, lifting lugs and paint. Look for oil, coolant or fuel residue that suggests a leak, and for rust or salt marks on bare surfaces.
Check nameplates and serial numbers against the documents and take close-up photos. Inspect cable and hose connections, battery isolation and desiccant or inhibitor labels. If the equipment arrives sealed for long-term storage, do not break the seal for curiosity; open only what you need and reseal it.
Count the parts and the loose items
Loose items travel separately: control cabinets, exhaust silencers, spare filters, tool kits, manuals and documentation. Count them against the packing list and look for anything that is crushed or exposed to moisture.
Record shortages immediately. A concise shortage report with part numbers, photographs and the signed delivery note gives the supplier and carrier what they need to react quickly and keeps the construction schedule honest.
Store and preserve after receipt
Once accepted, equipment often waits weeks before installation. Store it on timber or concrete rather than bare ground, keep covers intact, and maintain the preservation described by the manufacturer. Engines may need periodic barring and inhibitor checks, and electrical equipment may need heaters connected.
Log each inspection of stored equipment with date, condition and photographs. A weekly walk-round with simple records can be the difference between a smooth start-up and a month of delays when the equipment is finally energised. The wider plan is covered in our power logistics hub, and the heavy handling techniques in our jacking and skidding guide.
A short receiving checklist
A one-page checklist keeps the team consistent. Confirm documents and consignee. Photograph the truck, packing and each face of the load before unloading. Record shock and tilt indicator status. Note external damage on the delivery note and have the driver sign.
After unloading, count and check loose items, compare serial numbers, inspect visible components and record the preservation condition. Log everything with date, time, names and photographs, then file the report with the delivery documents so each item can be traced from the factory gate to its foundation.
A sensible target is to complete the first inspection within the same shift as the delivery. Hours matter, because rain, dust, theft and handling by other contractors can all muddy the question of where damage happened.
Teams that handle many deliveries often add a simple colour tag system on the laydown area: green for accepted and preserved, amber for open discrepancies, red for quarantined items. A glance at the yard then tells the construction manager what can be lifted today, and it prevents a damaged item from being installed by mistake because it happened to be the next one on the programme.
Report, close out and hand over
Issue a receiving report within a day or two, with the documents, photographs, discrepancy list and storage plan. Share it with procurement, the supplier, the carrier and the insurer as the contract requires, and keep the originals with the project file.
Handover to the construction team should include the status of each package, any restrictions on lifting or storage, and the open items from the report. Clear records also help later when the export documents and warranty data need to be matched to what actually arrived.
About the authors
This guide comes from the USP&E project logistics and construction engineers who receive and install power equipment on site. USP&E is an EPC and O&M contractor, not a broker, with 150+ power projects in 45+ countries, 25,000 MW contracted since 2002 and 24+ years in the field. Our power plant EPC projects page shows how logistics fits into project delivery.
Offices: Colorado Springs (1755 Telstar Dr, Suite 300), Knoxville (800 S Gay St, Suite 700), London (162-168 Regent Street), Johannesburg (22 Kildoon Rd, Bryanston), Cape Town (31 Brickfield Road, Woodstock) and China (No. 1 Ningzhou Road, Wuxi). Regions: USA | AFRICA | UK | UAE | CHINA. ISO 9001 and ISO 45001 certified.
Receiving inspection questions
What should be checked first when a generator arrives?
Compare the delivery documents with the order and packing list, then inspect the packing and equipment for visible damage before the carrier leaves.
Why write damage on the delivery note?
A note signed at delivery is strong evidence that damage occurred in transit, which supports a claim against the carrier or insurer.
How are shock and tilt indicators used?
They show whether the load was dropped or tipped. Photograph them in place and record their status on the delivery note.
Should sealed equipment be opened on receipt?
Only as much as the inspection needs, then reseal. Sealed preservation protects the engine or alternator until installation.
How should received equipment be stored?
Off the ground, covered and preserved as the manufacturer states, with regular recorded inspections.
Who needs the receiving report?
Procurement, the supplier, the carrier and the insurer as the contract requires, with the original kept in the project file.
Plan your site receiving
Send your delivery schedule and equipment list, and our team will suggest a receiving checklist and storage plan that fit your project.
Use the receiving plan request for a structured request, email info@uspeglobal.com with any site data you hold, or ring +27 10 822 2324 to speak to an engineer. Equipment from stock, already inspected before dispatch, is listed in our diesel generator inventory.