Jacking and Skidding Medium-Speed Generating Sets into Place

A medium-speed HFO or diesel generating set for a utility or mine power station can weigh well over 100 tonnes on its common baseframe. Getting it from the transport trailer onto its foundation inside an engine hall is often the riskiest single movement in the whole logistics chain, and cranes are not always the answer.

Where the hall roof is already on, the overhead crane is too light, or the ground will not support a large mobile crane, the set is usually jacked and skidded into place. This guide explains how that method works, the simple arithmetic behind it and the checks that keep the engine, the foundation and the team safe.

When to skid instead of lifting

Mobile crane lifts need space, firm ground and clear access, and a crane large enough to place a heavy genset at radius inside a building can be hard to source and move on remote sites. Overhead cranes in engine halls are normally sized for maintenance lifts such as cylinder heads and turbochargers, not for the complete set.

Jacking and skidding needs far less space and lighter equipment. The set is raised off the trailer with hydraulic jacks, moved horizontally along a temporary track into the hall and lowered onto its foundation. It is slower than a crane lift but often the safer and more practical choice. The method should be decided early, because it affects the hall doors, the floor and the delivery sequence covered in our article on shipping HFO engines to mines.

The method statement

A typical sequence is: position the trailer at the hall entrance, jack the set off the trailer in stages while building cribbing beneath it, withdraw the trailer, lower onto skid shoes sitting on a greased or low-friction track, push or pull the set along the track into the hall, jack it up again over the foundation, remove the track and lower it onto temporary supports or its final chocks.

Each step needs a written procedure, a named supervisor, defined communication signals and stop criteria. The method statement should be reviewed by the engine supplier, the civil engineer responsible for the foundation and the site safety lead before any equipment arrives.

Weight and centre of gravity

Everything starts with an accurate weight and centre of gravity for the set as shipped, including the baseframe and any fluids or accessories fitted. Engine and alternator makers publish these figures; use the shipping weight on the transport documents and the marked lifting and jacking points, not estimates.

Because the engine is heavier than the alternator, the centre of gravity is rarely in the middle of the baseframe. Jack loads are therefore uneven, and the jacking plan must allocate capacity to each point accordingly.

Choosing jacks and cribbing

Jacks are selected so that each one works well below its rated capacity at the heaviest point. For a 150 tonne set where the engine end carries 60 percent of the weight, the two engine-end jacking points share 90 tonnes, or 45 tonnes each. A 100 tonne jack at each point gives comfortable margin; synchronised hydraulic systems keep all points moving together.

Cribbing, usually hardwood or engineered timber laid in alternating layers, follows the set up and down so that it is never held only by the jacks. A common rule is to keep the cribbing stack no taller than about one and a half to two times its base width, and to raise the set in small lifts, adding cribbing at each step.

Skid track and push force

Skid tracks are steel beams with a low-friction surface, often PTFE pads on stainless steel or greased steel. The force needed to move the load is the weight multiplied by the friction coefficient. With a coefficient of about 0.05 to 0.1, moving a 150 tonne set takes roughly 7.5 to 15 tonnes of push or pull, well within the range of hydraulic push-pull units that grip the track.

Starting friction is higher than running friction, so plan for the higher figure, and add allowance if the track has any slope. The track must be level, continuous across joints and supported along its length, or the shoes will bind and loads will concentrate.

Ground and floor bearing

Every load path, from cribbing pads outside the hall to the track inside, must be checked for bearing capacity. If a 150 tonne set sits on four cribbing stacks, each with a one square metre base, the average pressure is 37.5 tonnes per square metre, or roughly 370 kilopascals, before allowing for uneven loading. Compacted fill outside a hall may not carry that without steel spreader plates or mats.

Inside the hall, the floor slab and any trenches or pits along the route need the same check. Our route planning article on heavy haul route surveys covers how similar bearing checks are made for roads, bridges and site access.

Hall and foundation readiness

Before the set moves, the foundation must have reached its specified concrete strength, holding-down bolt positions must be surveyed against the baseframe drawing, and the hall doors and clear height must be confirmed against the set dimensions plus jacking clearance. Cable trenches, pipe sleeves and drains should be finished or covered so that they do not obstruct the track.

It is far easier to correct a misplaced bolt pocket before the set arrives than with 150 tonnes sitting above it, so a dimensional check against the actual baseframe is a standard hold point.

Lowering, chocking and alignment

Over the foundation, the set is jacked up, the track removed and the set lowered onto temporary packing or adjustable supports at the specified height. Final steel or resin chocks are fitted later during alignment, following the maker’s procedure.

Alignment between engine and alternator, and the crankshaft deflection checks that confirm it, must be done after the set is in its final position, because transport and skidding can disturb it. Our power plant EPC delivery sequence places these checks before any engine run.

Preservation, hold points and records

Sets often wait days or weeks between arrival and commissioning. Keep preservation covers on, maintain any desiccant or dehumidification the maker specifies, turn the engine at the required interval and protect openings from dust and water while civil and electrical work continues around it.

Record every hold point: weight confirmation, jacking equipment certificates, cribbing inspection, track level check, foundation acceptance and final position survey. These records support insurance, warranty and the handover file, and they show the receiving operations team that the set arrived and was installed as the maker intended.

About the authors

This guide comes from the USP&E logistics coordinators and installation supervisors who move heavy generating plant from port to foundation on station projects. USP&E is an EPC and O&M contractor, not a broker, with 150+ power projects in 45+ countries, 25,000 MW contracted since 2002 and 24+ years in the field. Installed sets are then handed to our operations and maintenance teams.

Offices: Colorado Springs (1755 Telstar Dr, Suite 300), Knoxville (800 S Gay St, Suite 700), London (162-168 Regent Street), Johannesburg (22 Kildoon Rd, Bryanston), Cape Town (31 Brickfield Road, Woodstock) and China (No. 1 Ningzhou Road, Wuxi). Regions: USA | AFRICA | UK | UAE | CHINA. ISO 9001 and ISO 45001 certified.

Jacking and skidding questions

What is jacking and skidding?

A method of moving heavy equipment by raising it with hydraulic jacks, sliding it along a low-friction track and lowering it into position, without a large crane.

When is skidding used for generator sets?

When the engine hall roof is on, the overhead crane is too small, or ground and access do not allow a large mobile crane.

How much force is needed to skid a 150 tonne genset?

With a friction coefficient of about 0.05 to 0.1, roughly 7.5 to 15 tonnes of push or pull, plus allowance for starting friction and slope.

Why is cribbing used during jacking?

Cribbing follows the load up and down so it is never supported by the jacks alone, which protects against a jack failure.

Must alignment be rechecked after installation?

Yes. Transport and skidding can disturb engine to alternator alignment, so alignment and deflection checks are done in the final position.

What should be checked before the set arrives?

Foundation strength, bolt positions against the baseframe, door and height clearances, floor bearing and a clear, level track route.

Plan your heavy equipment installation

Send us the set weights, hall drawings and site access details, and our logistics engineers will help plan the transport, jacking and skidding sequence for your station.

Use the logistics planning enquiry form for a structured request, email info@uspeglobal.com with any site data you hold, or ring +27 10 822 2324 to speak to an engineer. Generating sets for station projects are listed in our power equipment inventory.


Where we operate

USA | AFRICA | UK | UAE | CHINA

USP&E United States

Colorado Springs Office: 1755 Telstar Dr, Suite 300

Knoxville Office: 800 S Gay St, Suite 700

USP&E South Africa

Johannesburg Office: 22 Kildoon Rd, Bryanston

Cape Town Office: 31 Brickfield Road, Woodstock

USP&E United Kingdom

London Office: 162-168 Regent Street

USP&E China

China Office: No. 1, Ningzhou Road, Wuxi

Call:+27 10 822 2324  |  E:info@uspeglobal.com

ISO Certifications
ISO9001ISO45001

Powering Possibility. Built for the Frontier.
Full-service EPC & O&M. Not a broker.

© 2026 USP&E · SmartPower Logistics is part of USP&E