A good survey prevents the costly moments everyone in project logistics fears, such as a transformer parked on a roadside for weeks because a bridge cannot take it. This guide explains how a heavy haul route survey is planned and run, and what the finished report should give the project team.
When to carry out the survey
The survey should start as soon as the equipment’s transport dimensions and weights are known with reasonable confidence, which is often during procurement rather than after the purchase order. Findings can affect the choice of port, the transport mode, the way a package is split for shipping, and even the site access road design.
Leaving it late is the common mistake. A survey that finds a weak bridge a few weeks before arrival leaves no time to strengthen it, find an alternative or redesign the shipment. A first survey early, followed by a confirmation run shortly before the move, is the safer pattern.
Defining the load
Everything starts with accurate load data for each heavy or oversize item. The transport drawings from the manufacturer should give length, width, height, gross weight, centre of gravity and lifting and lashing points. The transport contractor then adds the trailer configuration, which sets the axle loads, the overall combination length and the ground clearance.
The survey is only as good as these numbers. A turbine package that grows by a few hundred millimetres in height after a late design change can turn a clear route into a blocked one, so drawings should be frozen, or the survey repeated, when designs change. Our post on step-up transformer transport shows how much the trailer choice changes the picture for the heaviest item on most sites.
The desktop study
Before anyone drives the route, a desktop study narrows the options. It uses road maps, satellite imagery, road authority data on bridges and weight limits, and any records of previous abnormal moves on the same corridor. The aim is to pick one preferred route and at least one alternative, and to list every point that needs physical checking.
Typical items flagged at this stage include bridges and culverts, low structures such as gantries and overhead lines, tight junctions and roundabouts, steep gradients, level crossings, town centres and known roadworks.
The driven survey
The survey team then drives the route, often in both directions, recording each critical point with measurements, photographs and coordinates. Overhead clearances are measured with suitable instruments rather than estimated. Road widths, kerb heights, street furniture and verge conditions are noted at every pinch point.
Bends and junctions are checked against the swept path of the actual trailer combination. Swept path software models how the trailer and load move through a turn, showing where wheels leave the road surface or the load overhangs signs, walls or trees. Gradients are checked against the pulling and braking capacity of the tractor units, and road surfaces are assessed for soft ground or damage that could be made worse.
Bridges, culverts and buried services
Structures are usually the deciding factor for the heaviest loads. Each bridge and culvert on the route needs an assessment against the planned axle loads and spacing, normally by a structural engineer working with the road or rail authority that owns it. Outcomes range from simple approval, to conditions such as crawl speed and central positioning, to temporary strengthening or a bypass.
Buried pipes, cables and shallow culverts under the road also need attention, because a heavy trailer concentrates load in a way normal traffic does not. Owners of the services may require protection measures, such as temporary steel plates or mats, before they agree to the move.
Obstructions and utilities
Many routes are only passable once obstructions are temporarily moved. Traffic signs, street lights, barriers and signal heads can be unbolted and refitted. Overhead telephone and power lines may need to be lifted or switched off for a short time, which can only be arranged with the network owner and often weeks in advance.
The survey report should list each obstruction, its owner, the action needed and the notice period. That list becomes the backbone of the movement plan and feeds directly into the heavy-haul permit applications.
What the survey report should contain
A complete report allows the transport contractor, the permit authorities and the project team to work from the same facts. It should include:
- The load list with dimensions, weights and the trailer configuration assumed.
- The preferred route and alternatives, with maps and a point-by-point log.
- Clearance measurements and photographs at each critical point.
- Swept path drawings for difficult junctions.
- Structure assessments and any conditions attached to them.
- Obstructions, owners, required actions and notice periods.
- Recommended travel times, escort needs, parking and overnight stopping places.
- Open items and risks still to be resolved before the move.
Escorts, timing and contingency
Authorities usually set the travel window, often at night or at weekends to reduce disruption, and decide whether police or private escorts are needed. The plan should identify safe lay-bys where the convoy can stop if it falls behind or meets a problem, because a large load cannot simply pull over anywhere.
Contingency planning covers breakdowns, weather and unexpected obstructions. Spare tractor capacity, a recovery plan and contact details for every authority and utility along the route should travel with the convoy.
The last mile into site
The public road ends at the site gate, but the survey should not. Site access roads, temporary bridges, the turning area and the ground under the crane all need the same checks for width, bearing capacity and gradient. The handover from road transport to lifting is covered in our crane lift plan guidance.
Linking the route survey with the plant’s construction plan means the load arrives when the foundation and crane are ready, rather than waiting in a yard. That coordination is part of how we run delivery on EPC power plant projects.
About the authors
This guide comes from the SmartPower logistics and project engineering team that plans the movement of turbines, transformers and generator sets to remote power plant sites. USP&E is an EPC and O&M contractor, not a broker, with 150+ power projects in 45+ countries, 25,000 MW contracted since 2002 and 24+ years in the field. Once plant is installed, the same team supports spares and service under our operations and maintenance programmes.
Offices: Colorado Springs (1755 Telstar Dr, Suite 300), Knoxville (800 S Gay St, Suite 700), London (162-168 Regent Street), Johannesburg (22 Kildoon Rd, Bryanston), Cape Town (31 Brickfield Road, Woodstock) and China (No. 1 Ningzhou Road, Wuxi). Regions: USA | AFRICA | UK | UAE | CHINA. ISO 9001 and ISO 45001 certified.
Route surveys: quick answers
What is a heavy haul route survey?
A study of the full road route from port or factory to site, proving that an oversize or overweight load can pass every bridge, bend, structure and obstruction, and listing the actions needed where it cannot.
When should a route survey be done?
As soon as transport dimensions and weights are reliable, often during procurement, with a confirmation run shortly before the move.
Who assesses bridges on the route?
A structural engineer, normally working with the road or rail authority that owns each structure, using the planned axle loads and spacing.
What is a swept path analysis?
Software modelling of how the trailer and load move through a turn, showing where wheels leave the road or the load clips signs, walls or trees.
Can overhead lines be moved for a load?
Often, but only by arrangement with the network owner, who may lift or switch off the line for a short period with advance notice.
Does the survey include the site access road?
It should. Access roads, temporary bridges and crane ground need the same checks for width, bearing capacity and gradient as public roads.
Plan the move before the order ships